Hi,
You are requested to check -
1.Transfers made from other projects to this project, Since MAP on the receiving project is changed accordingly if its MAP for that material is different than that of sending projects
2.Plant stock and WBS price different
If the WBS (project stock) price is different than the plant stock price, the project stock moving average price is affected up or down proportionately.
For example: The plant stock moving average price is 5.00 each.The Project has 6 Qty on hand on one WBS with a total value of 60.00 (MAP= 10.00 each). A quantity of 4 was transferred from plant stock to that WBS via MB1B,The total value of movement is 20.00. The new total value of that project stock line is 80.00. The new quantity is 10. The new MAP for those 10 on that WBS is therefore 8.00.
3. Stock entries by 561 and its reversal 562 Movement with different amount in LC
Please refer following link which explains the MAP Behavior
Thanks
Message was edited by: k j